Daily Drill Report Hinkle Trust #1 & #2 Program
Hinkle Trust #1 Daily Drill Report
Project: Hinkle Trust #1 Permit # 060386
Effingham County, IL
SEC 11 TWP 06N RGE 05E    
January  2010
Day Date Operation            
Pre-Drill Thrusday Begin moving Webster Drilling rig components to #1 location.
14-Jan  Build lease road. Dig pits.
1 15-Jan Rig up and move water to location. 
Begin drilling surface hole for 8 5/8ths casing.
Cemented 84 ft. 8 5/8ths surface casing with 90 Sx.
2 18-Jan 7:00AM   Activity:Drilling     Formation:Shale and Lime
T.D.: 90 ft.
3 19-Jan 7:00AM   Activity:Drilling     Formation:Shale and Lime
T.D.:1080’   Footage Made: 1000’   Hrs. Dlg.: 13hrs
Hrs. Trip:None  Hrs. Circ.:1hr  Hrs. Maint.: 6hrs; changing Kelly bushing
Straight Hole Test: ¾ deg. @ 550’
Min./Ft.: 0   Hrs. J. & C.:  0  Hrs. Other: 4hrs; jetting pits
Jets - 6  # Size: 11   Hrs. On Bit: 13hrs Footage On Bit: 1000’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Straight Hole Test: ¾ deg. @ 550’
Straight Hole Test: ¾ deg. @ 1000’
4 20-Jan 7:00AM   Activity:Drilling     Formation:Shale and Lime
T.D.: 1933’   Footage Made: 853’   Hrs. Dlg.: 16hrs
Hrs. Trip: None   Hrs. Circ.: 1hr; Straight Hole Test    Hrs. Maint.: 1hr; Draw Works
Min./Ft.: 0   Hrs. J. & C.: 0 Hrs. Other: 6hrs; connections and jetting pits
Jets - 6  # Size: 11   Hrs. On Bit: 29hrs Footage On Bit: 1853’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Straight Hole Test: ¾ deg. @ 550’
Straight Hole Test: ¾ deg. @ 1000’
Straight Hole Test @ 1500’ is ¾ deg.  
5 21-Jan 7:00AM   Activity:Drilling     Formation:Shale and Lime
T.D.: 2442’   Footage Made: 509’   Hrs. Dlg.: 15hrs
Hrs. Trip:  1 hr; short trip   Hrs. Circ.: 4hr    Hrs. Maint.: none
Dev. % Ft.: 1/2 @ 2000’ Other:4 hrs; cons. and running straight hole test
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Jets - 6  # Size: 11   Hrs. On Bit: 44hrs Footage On Bit: 2362’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
Mud Wt.: 8.8  Vis.: 50 Filter Cake: 2/32 Chlorides: 700
GS: 2/4  CA: 0 LCM: 0  Solids %: 3.75  PH: 10
Water Loss: 0  PV: 20   YP: 12 Mud Pump: SPM 56 
Mud Pump Pressure: 800  psig.   Mud Pump Linear: 0
Straight Hole Test:@ 550’ is ¾ deg. 
Straight Hole Test:@ 1000’ is ¾ deg. 
Straight Hole Test @ 1500’ is ¾ deg.  
 Straight Hole Test @ 2000’ is ½ deg.
6 22-Jan 7:00AM   Activity: Drilling & Coring     Formation: Shale and Sand
T.D.: 2591’   Footage Made: 149’   Hrs. Dlg.: 5 hrs w/ PDC bit and 4 hrs w/ core bit
Hrs. Trip:  8hrs  Hrs. Circ.: 2hr    Hrs. Maint.: none
Hrs. Other: 5 hrs; core work
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Jets - 6  # Size: 11   Hrs. On Bit: 49hrs Footage On Bit: 2511’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
Remarks: Took core sample of cap rock w/ Rosiclare     
7 23-Jan 7:00AM   Activity: Waiting to get Mud Pump Fixed    Formation: 
T.D.: 2591’   Footage Made:   Hrs. Dlg.: 
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Jets - 6  # Size: 11   Hrs. On Bit: 49hrs Footage On Bit: 2511’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
8 24-Jan 7:00AM   Activity: Drilling     Formation: Lime
T.D.: 2775’   Footage Made: 184’   Hrs. Dlg.: 16hrs
Hrs. Trip: 2hrs; going back in the hole Hrs. Circ.:0  Hrs. Maint.: 1hr; change pistons and pump
Hrs. Other: 5hrs; waiting on part and putting pump together
Jets - 6  # Size: 11   Hrs. On Bit:65hrs  Footage On Bit: 2695’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Straight Hole Test:@ 550’ is ¾ deg. 
Straight Hole Test:@ 1000’ is ¾ deg. 
Straight Hole Test @ 1500’ is ¾ deg.  
Straight Hole Test @ 2000’ is ½ deg.
 Straight Hole Test @ 2500’ is ¼ deg.
9 25-Jan 7:00AM   Activity:Drilling  & Logging   Formation:Salem
T.D.: 2950’   Footage Made: 175’   Hrs. Dlg.: 4hrs
Hrs. Trip: 4hrs  Hrs. Circ.: 1 1/2hrs    Hrs. Maint.: none
Hrs Other:: 14 ½ hrs: Logging, Pipe and casing work
Bit #2  Mfg.: Reed  Type:BB  Size: 7 7/8 PDC
Jets - 6  # Size: 11   Hrs. On Bit: 69hrs Footage On Bit: 2870’
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
# Drill Collars: 15    Length: 453’  Drill Collar Thread: x-hole   Drill Collar Size: 6’’
Depth: 2852’  Mud Wt.: 9.0  Vis.:55  Filter Cake: 1/32 Chlorides: 700
GS: 3-6 CA: 0 LCM: 0  Solids %: 5.25  PH: 10
Water Loss: 7.8  PV: 24   YP: 16 Mud Pump: SPM 56 
Mud Pump Pressure: 800  psig.   Mud Pump Linear: 0
Straight Hole Test:@ 550’ is ¾ deg. 
Straight Hole Test:@ 1000’ is ¾ deg. 
Straight Hole Test @ 1500’ is ¾ deg.  
Straight Hole Test @ 2000’ is ½ deg.
 Straight Hole Test @ 2500’ is ¼ deg.
10 26-Jan 7:00AM   Activity:Ran 4 ½” Casing  to 2564’   Formation:McClosky
T.D.: 2950’  
Casing set at 2564 ft. with 375 sacks of cement. 
7 barrels were circulated back to surface (12:15PM-'1:00PM Monday) into pits.
Casing was ran to 2564’ to set packer
All operations on this well has ceased besides cutting the casing and nipple up.   



 Hinkle Trust #2 Daily Drill Report
Daily Drill Report
Project: Hinkle Trust #2 Permit # 060385
Effingham County, IL
SEC 11 TWP 06N RGE 05E    
January  2010
Day Date Operation            
Pre-Drill Friday Moved all drilling equipment and chemicals (mud) from 
29-Jan Hinkle Trust #1 location to Hinkle Trust #2 location. 
Skidded rig with mast up and prepared location for drilling.
Scheduled to begin drilling surface on Monday 02/01/10.
1 1-Feb Time of Report: 7:00AM        Activity: Rigging up to drill surface.    
2 2-Feb Time of Report: 8:00AM   Activity: Drlg.    Formation:
T.D.: 195’   Footage Made: 195’   Hrs. Dlg.: 11hrs
Hrs Other:  13hrs (note:1)
Bit #1  Mfg.: Reed  Type:BB  Size: Surface: 12 1/4" (note:2)
Jets - 8  # Size: 10   Hrs. On Bit: 11hrs  Footage On Bit: 95' (note:2)
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
Mud : Fresh Water
Note 1: Pumped water, drilled 84 ft. surface hole, ran 8 5/8” pipe, 
nipple up, and wait on cement.
Note 2: Drilled a 39’ deep rat hole with 8 3/4’’ bit.
Cemented 84 ft. 8 5/8” casing with 75 SX cement, plug down at 1:00 AM. 
3 3-Feb Time of Report: 7:00AM   Activity: Drlg.    Formation: Shale & Lime
T.D.: 1125’   Footage Made: 1030’   Hrs. Dlg.: 18hrs
Hrs. Trip: None   Hrs. Circ.:2 hrs  Hrs. Maint.: 1 hr; worked on mud pump
Hrs Other:  3 hrs; connections, jetting pits, and S.H.T
Bit #2  Mfg.: Reed  Type:PDC  Size: Surface: 7 7/8"
Jets - 6  # Size: 11   Hrs. On Bit: 29hrs  Footage On Bit: 1125'
Wt. On Bit: 6000lbs RPM: 60  Pipe Thread: x-hole Pipe Size: 4 ½’’
Drill Collars:15 Length:453’  Drill Collar Thread: x-hole   Drill Collar Size:6’’
Mud : Fresh Water
S.H.T. @ 500’ is 1 deg.
S.H.T. @ 1000’ is 1 deg.    
4 4-Feb Time of Report: 7:00AM   Activity: Drlg.    Formation: Shale & Lime
T.D.: 1972’   Footage Made: 847’   Hrs. Dlg.: 16hrs
Hrs. Trip: None   Hrs. Circ.:3 hrs; SHT and mud up Hrs. Maint.: none
Hrs. Other: 5 hrs; jet pits, pump water, and mud up
Bit #2  Mfg.: Reed  Type:PDC  Size: Surface: 7 7/8"
Jets - 6  # Size: 11   Hrs. On Bit: 34hrs  Footage On Bit: 1877' (note:1)
Wt. On Bit: 8000lbs RPM: 58  Pipe Thread: x-hole Pipe Size: 4 ½’’
Drill Collars:15  Length:453’  Drill Collar Thread: x-hole   Drill Collar Size:6’’
Mud : Fresh Water (Preparing to mud up)
Note 1: Footage on bit is TD minus 95’ drilled with surface bit.   
S.H.T. @ 500’ is 1 deg.
S.H.T. @ 1000’ is 1 deg.    
S.H.T. @ 1500’ is 1 deg.   
5 5-Feb Time of Report: 7:00AM   Activity: Drlg.    Formation: Sand & Lime
T.D.: 2550’   Footage Made: 578’   Hrs. Dlg.: 19hrs
Hrs. Trip: None   Hrs. Circ.:1 hr  Hrs. Maint.: none
Hrs. Other: 4 hrs; S.H.T., jet pits, and make connections
Bit #2  Mfg.: Reed  Type:PDC  Size: Surface: 7 7/8"
Jets - 6  # Size: 11   Hrs. On Bit: 53hrs  Footage On Bit: 2455'
Wt. On Bit: 12000lbs RPM: 52  Pipe Thread: x-hole Pipe Size: 4 ½’’
Drill Collars:15  Length:453’  Drill Collar Thread: x-hole   Drill Collar Size:6’’
Mud Depth: 2550’  Mud Wt.: 9.1  Vis.: 52   Filter Cake: 1/32 Chlorides:700
Water Loss:7.8    PV:8.0   YP:7.0
Mud Pump: SPM 54 Mud Pump Pressure: 800lbs psig.
S.H.T. @ 500’ is 1 deg.
S.H.T. @ 1000’ is 1 deg.    
S.H.T. @ 1500’ is 1 deg.   
S.H.T. @ 2000’ is 7/8 deg. 
6 6-Feb Time of Report: 7:00AM   Activity: Shutting  Down Operations
T.D.: 2550'
Past 24 hours, condition mud for logs, trip out of hole, Weatherford logs 
well, talley and run 2550 ft. 4 ½” production casing.  Schwartz on location 
to cement with 355 sx.  Circulated 9 barrels into pit. Plug down at 1:00 am.