| MDM Energy, Inc., Daily Drill Report Hinkle Trust #2 | ||||||||||||
| Daily Drill Report | ||||||||||||
| Project: | Hinkle Trust #2 Permit # 060385 | |||||||||||
| Effingham County, IL | ||||||||||||
| SEC 11 TWP 06N RGE 05E | ||||||||||||
| January | 2010 | |||||||||||
| Day | Date | Operation | ||||||||||
| Pre-Drill | Friday | Moved all drilling equipment and chemicals (mud) from | ||||||||||
| 29-Jan | Hinkle Trust #1 location to Hinkle Trust #2 location. | |||||||||||
| Skidded rig with mast up and prepared location for drilling. | ||||||||||||
| Scheduled to begin drilling surface on Monday 02/01/10. | ||||||||||||
| 1 | 1-Feb | Time of Report: 7:00AM Activity: Rigging up to drill surface. | ||||||||||
| 2 | 2-Feb | Time of Report: 8:00AM Activity: Drlg. Formation: | ||||||||||
| T.D.: 195’ Footage Made: 195’ Hrs. Dlg.: 11hrs | ||||||||||||
| Hrs Other: 13hrs (note:1) | ||||||||||||
| Bit #1 Mfg.: Reed Type:BB Size: Surface: 12 1/4" (note:2) | ||||||||||||
| Jets - 8 # Size: 10 Hrs. On Bit: 11hrs Footage On Bit: 95' (note:2) | ||||||||||||
| Wt. On Bit: 6000lbs RPM: 60 Pipe Thread: x-hole Pipe Size: 4 ½’’ | ||||||||||||
| Mud : Fresh Water | ||||||||||||
| Note 1: Pumped water, drilled 84 ft. surface hole, ran 8 5/8” pipe, | ||||||||||||
| nipple up, and wait on cement. | ||||||||||||
| Note 2: Drilled a 39’ deep rat hole with 8 3/4’’ bit. | ||||||||||||
| Cemented 84 ft. 8 5/8” casing with 75 SX cement, plug down at 1:00 AM. | ||||||||||||
| 3 | 3-Feb | Time of Report: 7:00AM Activity: Drlg. Formation: Shale & Lime | ||||||||||
| T.D.: 1125’ Footage Made: 1030’ Hrs. Dlg.: 18hrs | ||||||||||||
| Hrs. Trip: None Hrs. Circ.:2 hrs Hrs. Maint.: 1 hr; worked on mud pump | ||||||||||||
| Hrs Other: 3 hrs; connections, jetting pits, and S.H.T | ||||||||||||
| Bit #2 Mfg.: Reed Type:PDC Size: Surface: 7 7/8" | ||||||||||||
| Jets - 6 # Size: 11 Hrs. On Bit: 29hrs Footage On Bit: 1125' | ||||||||||||
| Wt. On Bit: 6000lbs RPM: 60 Pipe Thread: x-hole Pipe Size: 4 ½’’ | ||||||||||||
| Drill Collars:15 Length:453’ Drill Collar Thread: x-hole Drill Collar Size:6’’ | ||||||||||||
| Mud : Fresh Water | ||||||||||||
| S.H.T. @ 500’ is 1 deg. | ||||||||||||
| S.H.T. @ 1000’ is 1 deg. | ||||||||||||
| 4 | 4-Feb | Time of Report: 7:00AM Activity: Drlg. Formation: Shale & Lime | ||||||||||
| T.D.: 1972’ Footage Made: 847’ Hrs. Dlg.: 16hrs | ||||||||||||
| Hrs. Trip: None Hrs. Circ.:3 hrs; SHT and mud up Hrs. Maint.: none | ||||||||||||
| Hrs. Other: 5 hrs; jet pits, pump water, and mud up | ||||||||||||
| Bit #2 Mfg.: Reed Type:PDC Size: Surface: 7 7/8" | ||||||||||||
| Jets - 6 # Size: 11 Hrs. On Bit: 34hrs Footage On Bit: 1877' (note:1) | ||||||||||||
| Wt. On Bit: 8000lbs RPM: 58 Pipe Thread: x-hole Pipe Size: 4 ½’’ | ||||||||||||
| Drill Collars:15 Length:453’ Drill Collar Thread: x-hole Drill Collar Size:6’’ | ||||||||||||
| Mud : Fresh Water (Preparing to mud up) | ||||||||||||
| Note 1: Footage on bit is TD minus 95’ drilled with surface bit. | ||||||||||||
| S.H.T. @ 500’ is 1 deg. | ||||||||||||
| S.H.T. @ 1000’ is 1 deg. | ||||||||||||
| S.H.T. @ 1500’ is 1 deg. | ||||||||||||
| 5 | 5-Feb | Time of Report: 7:00AM Activity: Drlg. Formation: Sand & Lime | ||||||||||
| T.D.: 2550’ Footage Made: 578’ Hrs. Dlg.: 19hrs | ||||||||||||
| Hrs. Trip: None Hrs. Circ.:1 hr Hrs. Maint.: none | ||||||||||||
| Hrs. Other: 4 hrs; S.H.T., jet pits, and make connections | ||||||||||||
| Bit #2 Mfg.: Reed Type:PDC Size: Surface: 7 7/8" | ||||||||||||
| Jets - 6 # Size: 11 Hrs. On Bit: 53hrs Footage On Bit: 2455' | ||||||||||||
| Wt. On Bit: 12000lbs RPM: 52 Pipe Thread: x-hole Pipe Size: 4 ½’’ | ||||||||||||
| Drill Collars:15 Length:453’ Drill Collar Thread: x-hole Drill Collar Size:6’’ | ||||||||||||
| Mud Depth: 2550’ Mud Wt.: 9.1 Vis.: 52 Filter Cake: 1/32 Chlorides:700 | ||||||||||||
| Water Loss:7.8 PV:8.0 YP:7.0 | ||||||||||||
| Mud Pump: SPM 54 Mud Pump Pressure: 800lbs psig. | ||||||||||||
| S.H.T. @ 500’ is 1 deg. | ||||||||||||
| S.H.T. @ 1000’ is 1 deg. | ||||||||||||
| S.H.T. @ 1500’ is 1 deg. | ||||||||||||
| S.H.T. @ 2000’ is 7/8 deg. | ||||||||||||
| 6 | 6-Feb | Time of Report: 7:00AM Activity: Shutting Down Operations | ||||||||||
| T.D.: 2550' | ||||||||||||
| Past 24 hours, condition mud for logs, trip out of hole, Weatherford logs | ||||||||||||
| well, talley and run 2550 ft. 4 ½” production casing. Schwartz on location | ||||||||||||
| to cement with 355 sx. Circulated 9 barrels into pit. Plug down at 1:00 am. | ||||||||||||