Daily Drill Report Hinkle/Keller Prospect

Hinkle #3 Daily Drill Report

Project:

Hinkle #3
Permit # 060695
Effingham County, IL
SEC 11 TWP 06N    RGE 05E

 
     
  April 2011  

 

Day Date Operation    
         
1 Sunday, April 3 9:00 AM Began drilling @ 8:30 PM on Sat. 
Set 95 ft. of 8 5/8ths surface casing.
Schwartz cements with 100 SX. Plug down at 6:00 AM.
Scheduled to resume drilling at noon.
   
         
2 Monday, April 4 7:30 AM Resumed drilling at 1:30PM Sunday.
Drilling at 880 ft. with water.
Straight hole test @ 500 ft. = 1 degree
Conditions: muddy, raining.
   
         
3 Tuesday, April 5 8:00 AM Drilling at 1730 ft. 
Preparing to convert from water to mud @ 1800 ft.
Straight hole test: 1000 ft. = 1/2 degree
                           1500 ft. = 1 1/4 degree
Conditions, windy and sunny.
   
         
4 Wednesday, April 6 7:30 AM Drilling at 2309 ft.  Began drilling with mud at 1800 ft.
Straight hole test @ 2000 ft. = 3/4 degree
Conditions: windy and sunny.
   
         
5 Thursday, April 7 7:00 AM TD. @ 2548 ft. @ 9:30 PM Wed.
U. McCloskey, good show of oil w/ strong odor. Sheen and oil in pits.
1:00 AM Weatherford on loc. to log well.
3:00 AM Finish logging, begin condition well for 4 1/2" casing.
7:00 AM Finish laying down drill pipe, prepare to set 4 1/2" casing.
   
         
6 Friday, April 8 Schwartz cements 2547 ft. of 4 1/2" production casing w/ 345 sacks.
Plug down at 11:30 AM.
Dig pits and prep  #4 location. Webster Drlg. rig down and move to Hinkle #4.
   
         

 




Hinkle #4 Daily Drill Report

Project:

Hinkle #4
Permit # 061043
Effingham County, IL
SEC 11 TWP 06N    RGE 05E

 
     
  April 2011  

 

Day Date Operation    
         
1 Friday, April 8 7:30 AM  Begin drilling surface for 8 5/8" surface casing.    
         
2 Saturday, April 9 8:00 AM Drilling at 130 ft.
Set 93 ft. 8 5/8" surface casing. Schwartz cements with 90 sacks.
Plug down at 9:50 PM Friday. Resumed drilling at 6:00 AM.
Conditions: heavy rain, some hail, localized flooding.
   
         
3 Sunday, April 10 7:30 AM Drilling at 1185 ft.
Straight hole tests; 500 ft = 1 degree
                           1000 ft. = 3/4 degree
Conditions; Muddy, sunny and warm.
   
         
4 Monday, April 11 7:30 AM  Drilling at 2023 ft.
Drilling with mud at 1800 ft.
Straight hole test @ 1500 ft. = 1 degree
   
         
5 Tuesday, April 12 7:30 AM Drilling at 2535 ft. to TD of 2540 ft.
Very good show of oil and gas in Upper McCloskey Oolites.
Straight hole test @ 2000 ft. = 1 1/2 degree.
Weatherford set to log well.
Conditions; clear sky, very muddy.
   
         
6 Wednesday, April 13 TD @ 2544 ft. at 8:30 AM Tues.
Weatherford logs well at 2:30 PM Tues.
Schwartz cements 2544 ft. 4 1/2" production casing w/360 sacks.
Plug down at 12:15 AM Wed. 12 barrels return to pits.
Webster rigging down and moving off location. 
   
         

 




Keller #8 Daily Drill Report

Project:

Keller #8
Permit # 060606
Effingham County, IL
SEC 11 TWP 06N    RGE 05E

 
     
  March 2011  

 

Day Date Operation    
         
PreDrill Thursday, March 24  Start moving rig components to location. Begin digging pits.    
         
  Friday, March 25 Rig up. Finish pits.    
         
1 Monday, March 28 Fill pits with water, begin drilling surface hole.    
         
2 Tuesday, March 29 Set 85 ft. 8 5/8ths surface casing. Schwartz cemented with 60 sacks. Plug down at 10:30 PM (Mon.). Working on swivel, set to resume drilling at 9:30 AM.    
         
3 Wednesday, March 30 7:00 AM Drilling with water at 1110 ft. Straight hole test @ 500 ft. = 1 degree. Straight hole test @ 1000 ft. = 1 degree.    
         
4 Thursday, March 31  Drilling at 1956 ft. Began mudding up at 1800 ft. First call depth at 2170 ft. (Barlow). Straight hole test; 1500 ft. = 3/4 degree.    
         
5 Friday, April 1 7:00 AM. Drilling at 2493 ft. Good show of oil in upper McCloskey @ 2475 - 2480. Straight hole test @ 2000 ft. = 3/4 degree.    
         
Saturday, April 2 T.D. @ 2515 ft. at 11:00 AM Fri.
Weatherford log well @ 3:00 PM Fri.
Run 2515 Ft. of 4 1/2" production casing.
Schwartz cements with 355 sx. Plug down @ 11:00 PM Fri.
7:00 AM Sat. Webster begins moving rig to Hinkle #3 loc. 
Digging pits and building location.