| Project: | Keller #6 Permit # 060611
|
|
|---|---|---|
| July 2010 |
| Day | Date | Operation | ||
| Pre-Drill | Sunday, July 4 | Moved Webster Drilling rig, dog house, and mud pumps onto location, dug pits and drilled rat hole. Ordered mud and pipe for delivery to loc. |
||
| 1 | Monday, July 5 | Begin drilling operations. Set 84 ft. 8 5/8ths surface casing. Cemented with 80 sacks. Plug down at 1:15 PM. Let cement set. Resume drilling at 8:00 PM |
||
| 2 | Tuesday, July 6 | 10:00 AM Drilling at 850 ft. with fresh water. Straight hole test at 550 ft = 1 degree. |
||
| 3 | Wednesday, July 7 | 7:30 AM Drilling at 1750 ft. with fresh water. Mud up at 1800 ft. 1st call depth 2170 ft. Straight hole test at 1050ft.=1 degree | 1500ft.=1/4 degree. |
||
| 4 | Thursday, July 8 | 7:30 AM Drilling 2350ft. with mud. Phil Caserotti on location to check samples. Straight hole test at 2000ft. =1 degree. |
||
| 5 | Friday, July 9 | 7:30 AM Total Depth at 2570ft. Weatherford log well 11:00PM Thurs. Run 2570ft. 4 1/2 Production casing with 325 sacks of cement. Plug down at 12:45PM. Rig down to move onto #7 location. |
||