MDM Energy Inc. Daily Drill Report Keller 7

Project:

Keller #7 Permit # 060612
Effingham County, IL
SEC 11 TWP 06N RGE 05E

 
     
  July 2010  

 

Day Date Operation    
         
Pre-Drill Saturday, July 10 7:30AM Rig-up on #7 loaction. Digging pits, prepare to begin drilling
operations; rathole, surface, etc.
   
         
1 Sunday, July 11 7:30AM Waiting on cement to set. Ran 88' of 8 5/8 surface casing.
Shwartz cemented with 66 sacks. Plug down at 3:00AM
Resume drilling at 10:30AM
   
         
2 Monday, July 12 7:30AM Drilling at 1250' with fresh water.
Straight hole test - 500'=1/2 degree | 1000'=1/4 degree
   
         
3 Tuesday, July 13 7:30AM Drilling at 2226' with mud. Straight hole test - 1600'=3/4 degree | 2100'=1 degree
Next call depth at 2450'
   
         
4 Wednesday, July 14 3:30AM Weatherford logs well. Preparing to run 2570' 4 1/2 production casing and cement.
7:30AM T.D. 2570' at 10:00PM Tuesday condition borehole for logging.
   
         
5 Thursday, July 15 Ran 2570' of 41/2" production casing.Cemented with 380 sacks. Plug down at 4:00PM.
Prepare to rig down and move off location.