Daily Drill Report Keller #1 & #2 Program
Keller #1 Daily Drill Report
Project: Keller #1 Permit # 059977
Effingham County, IL
SEC 11 TWP 06N RGE 05E    
September  2009
Day Date Operation            
1 24-Sep RDMO from previous loc.  Truck Geo. N. Mitchell Drlg Co Rig #1 to
subject well, RURT.  Will commence drlg operations tomorrow.
2 25-Sep Finish RURT, lay xtra wtr line, pmp wtr, commence drlg 12 1/4" surface hole.
3 26-Sep Depth 815', drlg(3min/5'), 24hr footage(815'). HOB #2(7:14). Dev surv(3/4 @596'). 
Drlg w/frsh wtr.
Past 24hrs: finish RURT, drill 12 1/4"surf hole, run: (45' of 8 5/8"csg set @50')cmt 
w/60sx 3%CaCl-2. PD @(11:30AM 9/25/09). WOC~start 7 7/8"hole @(7:30PM 9/25/09). 
4 27-Sep Depth 1836', drlg (2-3min/ft.), 24 hr footage (1021').  HOB #3 (8:50).  Dev surv (1/2 @
843', 1/2 @ 1091', 1/2 @ 1340', 1 @ 1585', 2 @ 1743', 1 1/4 @ 1804').  Vis 40, mud wt 9.
Past 24hrs: TOH~bit chng.
5 28-Sep Depth 2210', drlg (2min/ft), 24 hr footage (374').  HOB #3 (28:43).  Dev surv (1 1/2 @
1900', 1 1/2 @ 1998', 2 @ 2061', 1 1/4 @ 2121').  Vis 52, mud wt 9.2, wtr loss 8.8, 
pH 10.
6 29-Sep Depth 2454', TIH & resume drlg after running DST#1!!  At test depth was drlg 
24 hr footage (244').   HOB #3 (38:37).  Dev serv (3/4 @ 2216').  Vis 75, mud wt 9.3, 
wtr 7.8, pH 10. 
Past 24 hrs:  Short trip, cond hole, TOH, TIH run DST #1.
7 30-Sep Depth 2550', TD @ (1:00PM 9/29/09), presently prepare to NU to 4 1/2" csg, RMDO
loc. 
Past 24 hrs:  Finish TIH after DST #1, resume drlg operations.  At TD was drlg (5min/ft),
24hr footage (96').  HOB #3 (44:13).  Logged well, TIH, TOH~LDDP, run long string: (52jts~4
1/2"csg set @ 2546') cmt w/400sx, had 3bbls return to pit. PD @ (2:30AM 9/29/09).  RDMO
loc today.



Keller #2 Daily Drill Report
Project: Keller #2 Permit # 060262
Effingham County, IL
SEC 11 TWP 06N RGE 05E    
October  2009
Day Date Operation            
Pre-Drill Monday Surveyor stakes location and gps elevation.  Webster Drilling Services
19-Oct begin moving onto location and start digging pits, laying water lines,
and rigging up.  Scheduled to begin drilling on Tues.
1 20-Oct 7:00AM 490':  Past 24 hrs. Finish rig up, dig pits, drill rat hole, drill surface 
and set 50' 8 5/8; cement 50' plug down @ 5:30PM.  
Resume drilling @ 11:39PM.
Hrs on bit: 2, wt. on bit: 6000, RPM: 59. Pipe size: 4 1/2.
2 21-Oct 7:00AM 1690': 24hr footage 1200'.  Bit  #1; wt on bit 6000, RPM 59.
Dev surv. 1 @ 1500'. Mud: fresh water @ 1690'
3 22-Oct 7:00AM 2411': 24hr footage 721'.  Bit #1; wt on bit 6000, RPM 59.
Dev surv. 1 1/4 @ 2000'.  Mud wt: 9.0, Vis 4.4, pH 10.
Barlow 6ft high to Keller #1
4 23-Oct 7:00AM T.D. 2550':  24hr footage 139'.  Bit #1; wt on bit 6000, RPM 59.
Dev surv. 3 @ 2550'.  Mud wt: 9.0, Vis 42, pH 10.
7 ft. fill @ bottom while logs run.  Trip back in hole to circulate for 1 1/2 hrs.
after logging.  More fill while running 4 1/2 prod casing, had to circulate down. 
Schwartz cements w/375 sx.  Circulate 4 barrels into pit. Plug down @
9:30AM (Sat.).  Clean up location and road.  Shut down.