| Project: | Keller #6 |
|
|---|---|---|
| July 2010 |
| Day | Date | Operation | ||
| Pre-Drill | Sunday, July 4 | Moved Webster Drilling rig, dog house, and mud pumps onto location, dug pits and drilled rat hole. Ordered mud and pipe for delivery to loc. |
||
| 1 | Monday, July 5 | Begin drilling operations. Set 84 ft. 8 5/8ths surface casing. Cemented with 80 sacks. Plug down at 1:15 PM. Let cement set. Resume drilling at 8:00 PM |
||
| 2 | Tuesday, July 6 | 10:00 AM Drilling at 850 ft. with fresh water. Straight hole test at 550 ft = 1 degree. |
||
| 3 | Wednesday, July 7 | 7:30 AM Drilling at 1750 ft. with fresh water. Mud up at 1800 ft. 1st call depth 2170 ft. Straight hole test at 1050ft.=1 degree | 1500ft.=1/4 degree. |
||
| 4 | Thursday, July 8 | 7:30 AM Drilling 2350ft. with mud. Phil Caserotti on location to check samples. Straight hole test at 2000ft. =1 degree. |
||
| 5 | Friday, July 9 | 7:30 AM Total Depth at 2570ft. Weatherford log well 11:00PM Thurs. Run 2570ft. 4 1/2 Production casing with 325 sacks of cement. Plug down at 12:45PM. Rig down to move onto #7 location. |
| Project: | Keller #7 |
|
|---|---|---|
| July 2010 |
| Day | Date | Operation | ||
| Pre-Drill | Saturday, July 10 | 7:30AM Rig-up on #7 loaction. Digging pits, prepare to begin drilling operations; rathole, surface, etc. |
||
| 1 | Sunday, July 11 | 7:30AM Waiting on cement to set. Ran 88' of 8 5/8 surface casing. Shwartz cemented with 66 sacks. Plug down at 3:00AM Resume drilling at 10:30AM |
||
| 2 | Monday, July 12 | 7:30AM Drilling at 1250' with fresh water. Straight hole test - 500'=1/2 degree | 1000'=1/4 degree |
||
| 3 | Tuesday, July 13 | 7:30AM Drilling at 2226' with mud. Straight hole test - 1600'=3/4 degree | 2100'=1 degree Next call depth at 2450' |
||
| 4 | Wednesday, July 14 | 3:30AM Weatherford logs well. Preparing to run 2570' 4 1/2 production casing and cement. 7:30AM T.D. 2570' at 10:00PM Tuesday condition borehole for logging. |
||
| 5 | Thursday, July 15 | Ran 2570' of 41/2" production casing.Cemented with 380 sacks. Plug down at 4:00PM. Prepare to rig down and move off location. |
||